Making PPPs work for metro-rails: Early land acquisition is non-negotiable

Business Standard LogoBusiness Standard7h ago

Making PPPs work for metro-rails: Early land acquisition is non-negotiable - Business Standard

Quick Summary:

There are three reasons to expect that projects procured using the PPP model will be efficient on timelines, budget adherence and quality compliance.

Policies mandate that the project proposal must include the infrastructure for integration of various modes of transport, seamless transfer between various stations, and common payment instrument for ensuring last-mile connectivity.

In an EPC model the government entity is responsible for financing, procuring and operating the project and retains ownership of the project.


More Pictures

Making PPPs work for metro-rails: Early land acquisition is non-negotiable - Business Standard (Picture 1)

or

Article Details

Category: BusinessFinance

Markets:

Topics:

Source Website Secure: Yes (HTTPS)

News Sentiment: Neutral

Fact Checked: Legitimate

Article Type: News Report

Published On: 2025-04-23 @ 18:16:51 (7 hours ago)

News Timezone: GMT +5:00

News Source URL: business-standard.com

Language: English

Article Length: 979 words

Reading Time: 6 minutes read

Sentences: 53 lines

Sentence Length: 19 words per sentence (average)

Platforms: Desktop Web, Mobile Web, iOS App, Android App

Copyright Owner: © Business Standard

News ID: 28171268

View Article Analysis

About Business Standard

Business Standard Logo

Main Topics: BusinessFinance

Official Website: business-standard.com

Update Frequency: 257 posts per day

Year Established: 1975

Headquarters: India

News Last Updated: 3 hours ago

Coverage Areas: India

Ownership: Independent Company

Publication Timezone: GMT +5:00

Content Availability: Worldwide

News Language: English

RSS Feed: Available (XML)

API Access: Available (JSON, REST)

Website Security: Secure (HTTPS)

Publisher ID: #49

Publisher Details

Frequently Asked Questions

How long will it take to read this news story?

The story "Making PPPs work for metro-rails: Early land acquisition is non-negotiable" has 979 words across 53 sentences, which will take approximately 5 - 9 minutes for the average person to read.

Which news outlet covered this story?

The story "Making PPPs work for metro-rails: Early land acquisition is non-negotiable" was covered 7 hours ago by Business Standard, a news publisher based in India.

How trustworthy is 'Business Standard' news outlet?

Business Standard is a fully independent (privately-owned) news outlet established in 1975 that covers mostly business and finance news.

The outlet is headquartered in India and publishes an average of 257 news stories per day.

It's most recent story was published 3 hours ago.

What do people currently think of this news story?

The sentiment for this story is currently Neutral, indicating that people are not responding positively or negatively to this news.

How do I report this news for inaccuracy?

You can report an inaccurate news publication to us via our contact page. Please also include the news #ID number and the URL to this story.
  • News ID: #28171268
  • URL: https://chronographically.beamstart.com/news/making-ppps-work-for-metro-17454129946162

BEAMSTART

BEAMSTART is a global entrepreneurship community, serving as a catalyst for innovation and collaboration. With a mission to empower entrepreneurs, we offer exclusive deals with savings totaling over $1,000,000, curated news, events, and a vast investor database. Through our portal, we aim to foster a supportive ecosystem where like-minded individuals can connect and create opportunities for growth and success.

© Copyright 2025 BEAMSTART. All Rights Reserved.